Step 1: Calculate Required Line Speed Before Specifying Any Machine
Line speed should be calculated from the production target, not estimated from the machinery catalogue. The calculation works backward from annual volume to required bottles per minute:
- Annual production target (in units/year)
- Divide by the number of production days per year to get units per production day
- Divide by the number of productive hours per shift and shifts per day to get units per hour
- Apply an Overall Equipment Effectiveness (OEE) factor — typically 65–80% for a well-run filling line. This accounts for planned stoppages (changeovers, cleaning, breaks) and unplanned stoppages (jams, maintenance).
- The result — units per hour divided by OEE — is the required machine nameplate speed
Example: 10 million units per year, 250 production days, one 8-hour shift, 70% OEE = 10,000,000 ÷ 250 ÷ 8 ÷ 0.70 = 7,143 bottles per hour nameplate speed required.
This number is the minimum specification for every machine on the line. Do not accept machines rated below this speed — a line is only as fast as its slowest machine.
Step 2: Define the Process Stages Before Choosing Machines
Before evaluating any specific machine, map every process stage the product requires from empty container to finished case. A typical complete bottle line includes:
- Bulk bottle storage (pallet, bin, or bag) → unscrambler
- Conveying from unscrambler to rinser
- Air or water rinser (required for food and pharmaceutical applications)
- Conveying from rinser to filler with accumulation buffer
- Filling machine
- Conveying from filler to capper with accumulation buffer
- Cap feeder + capping machine
- Induction sealer (where tamper evidence or shelf life extension is required)
- Conveying to labeller
- Labelling machine (front, back, neck as required)
- Date coder (inkjet, laser, or print-and-apply)
- Check-weigher with reject station
- Case packer or shrink wrapper
- Case sealer (if using corrugated cases)
- Palletiser (manual, semi-auto, or robotic)
Not every line includes all stages. Lines for non-food products may omit rinsing; some products do not need induction sealing. But listing every stage before machine selection ensures that no process step is overlooked until after machines have been ordered — the most expensive oversight in line planning.
Step 3: Select the Filling Machine Last Among the Primary Machines
This is counterintuitive — the filling machine is usually specified first. The problem with specifying the filler first is that its configuration determines the capper configuration, which determines the unscrambler format, which determines the conveyor widths. If the filler is changed later (because a different filling method is required), several upstream and downstream decisions must be revisited.
The more reliable sequence for primary machine selection:
- Define the closure type first (screw cap, press-on, pump, etc.) — this determines the capping machine, which in turn determines the bottle handling approach throughout the line.
- Select the labelling method (pressure-sensitive, sleeve, or no-label) — this determines bottle body treatment and label application position.
- Select the secondary packaging format (case, tray, shrink) — this determines the line exit configuration.
- Now select the filling machine based on the product parameters established in your pre-project assessment.
- Design the conveying and accumulation system around the confirmed primary machines.
Step 4: Design Accumulation Into the Line from the Start
Accumulation conveyors between machines are not an add-on — they are an integral part of line performance. Without adequate accumulation, one machine stopping for 30 seconds cascades into the entire line stopping within 10–15 seconds. With adequate accumulation, a 30-second stop at one machine allows the adjacent machines to continue running, protecting production rate.
Accumulation buffer sizing guidelines:
- Between the unscrambler and filler: minimum 60 seconds of full-speed production capacity
- Between the filler and capper: minimum 30 seconds of full-speed production capacity
- Between the capper and labeller: minimum 45 seconds of full-speed production capacity
- Between the labeller and case packer: minimum 60 seconds of full-speed production capacity
These buffers allow minor stoppages (cap jam, label roll change, occasional rejected bottle) to be resolved without cascading across the line. Lines without adequate accumulation spend a disproportionate fraction of their operating time restarting rather than running.
Step 5: Specify Conveyor Width and Speed for the Slowest Machine's Format
The conveyor specification must accommodate the widest bottle in the SKU range, not the most common bottle. If you ever plan to run a wider bottle than the current range, specify the wider guide rail clearance now — retrofitting conveyor rail changes across a line is disproportionately expensive after installation.
Conveyor speed should be specified at 110–120% of the machine nameplate speed. This headroom prevents the conveyor from becoming the speed constraint when machines are running at their rated maximum, and it provides enough conveyor throughput to feed accumulation sections without starving them.
Step 6: Confirm Utility Requirements Before Construction
A bottle line requires compressed air, electrical power, and drainage at specific points on the production floor. These must be confirmed and planned before the facility is built or before a machinery installation is contracted — not during installation, when changes to floor penetrations and utility runs are expensive and disruptive.
Collect from each machine supplier:
- Compressed air: required pressure (bar), continuous consumption (L/min), and peak demand
- Electrical: connected kW per machine, voltage and phase, control voltage
- Water: connection requirements for CIP systems or water rinsers, inlet pressure and flow rate
- Drainage: location and size of drain connections for product spillage, rinse water, and CIP return
Aggregate these values across all machines to produce a utility load schedule. Share it with the facility engineer before construction or renovation begins.
The Most Common Planning Mistakes — and How to Avoid Them
- Buying the filler before specifying the closure: Cap type determines capping machine format, which determines bottle handling throughout the line. Fix the closure first.
- Specifying machines without accumulation conveyors: Every machine will stop occasionally. Accumulation is not optional — it is what makes the difference between a 65% and an 80% OEE line.
- Buying machines from multiple suppliers without a system integrator: When a jam occurs at the interface between Supplier A's filler and Supplier B's capper, both suppliers will point at the other. Specify and contract the entire line — or at least the conveying system — through a single responsible party.
- Not confirming floor load capacity before installing heavy equipment: A multi-head filler with a full product tank can weigh 2–4 tonnes. Confirm the floor load rating with a structural engineer before installation.
- Delivering all machines before the facility is ready: Machines stored outside or in an undamaged state for months before installation are a warranty and damage risk. Phase deliveries to coincide with installation readiness.
Planning a New Bottle Line?
Share your product type, bottle format, target production speed, number of SKUs, and available facility details. Our engineering team will review the project scope and provide a preliminary line specification, machine sequence, and accumulation layout recommendation — at no cost and with no commitment required.
Start Your Line Planning Discussion